Minutes of the Booster Supervisor Meeting held on 08.05.2012 Present: A. Findlay, G. Kruk, A. Lombardi, B. Mikulec, E. Ovalle, R. Rumolo, J. L. San
Figure 1. Intensity out of the PSB, as a function of the quadrupole setting. A.Lombardi → R. Wegner The Linac2 has been running quite well last
Wednesday 2/5/12 A 1 hour intervention by the BI team to replace the head amplifiers for the pick-ups in BTP10 & BTP30 solved the bad acquisition
the CCC and could see that, for an unknown reason, there were a number of parameters that were not used in the SFTPRO cycle that showed up in the Onl
At 10H00 the Linac Sup was called again due to intensity fluctuations returning, she suspected LI.CBU02 and retuned onsite to investigate. The investi
4. Isolde (from Emiliano) E.Piselli → P.Fernier HRS: Beam to users on Tuesday. Power glitch early in the morning…and 2 vacuum glitch in the target s